Case study · East Auckland

A 49m² Auckland extension, costed honestly

$240,079

Total incl GST. $4,900 per m², completed 2026

See the cost breakdown

Every figure on this page comes from the invoices and timesheets on this build. Homeowners often ask us what an extension actually costs in Auckland, so here is one of ours, line by line.

Drone view of the finished Mellons Bay extension: white weatherboards, a flat roof and a timber deck with a black balustrade, beside the existing house

How this job compares: our Auckland extension cost guide puts it side by side with our other jobs.

What did we build in Mellons Bay?

A 49m² single-storey extension on the back of a two-storey house in Mellons Bay. It added a master bedroom with a walk-in robe, an ensuite and an open-plan living area that opens onto a deck. The client lives with mobility needs, so it had to give real wheelchair access, not just the code minimum.

A red brick chimney on the outside wall of the house, with paving in front and the garden sloping away behind
BeforeThe brick chimney on the outside of the house, before the extension.
The chimney painted white inside the new living area, with a TV cabinet beside it, a skylight above and glass doors to the deck
AfterThe same chimney, now inside the new living area.

It is 49m² on purpose. Past 50m² the job would have needed a stormwater detention tank and resource consent. There's more on that further down.

Floor plan and elevations of the extension: walk-in robe, ensuite, bedroom and living area, joined to the kitchen and lounge of the existing house
The plan. The extension is in blue, on the back of the existing house.

What did it cost, line by line?

$240,079 including GST for the finished extension, or $4,900 per m². Nothing below is rounded, and nothing is averaged against other jobs. These are from 2026.

Scroll the table sideways →

Mellons Bay extension · all figures incl GST
ItemDescriptionCost
Construction labourSkilled trade labour at commercial rates$77,447
Construction materialsTimber, fixings, GIB, Pink Batts, Ecoply, hardware$49,404
Aluminium joineryStacker slider, bifold, awning, hinged door, thermally broken Low-E$19,600
FlooringTimber overlay plus underlay and prep$19,186
ElectricalRough-in, heat pump pre-pipe, fit-out, switchboard upgrade$11,776
DrainageDrainage, stormwater connections, pile drilling, foundation work$10,820
Council consent feesProcessing, inspections and levies, passed through at cost$6,833
TilingPorcelain tile, tiling labour, waterproofing, adhesive$7,595
Wall claddingRusticated weatherboards plus corrugated steel to one rear wall$7,247
PlumbingBathroom rough-in, hot water cylinder, accessible fittings$6,782
Roof claddingLong-run colour steel skillion roof at 8 degrees$6,996
Bathroom fittingsVanity basin, accessible WC, level-entry shower drain, mixers$6,233
Design and draftingFull BC-ready plan set by an LBP-registered draftsman$6,021
Heat pumpDaikin 5.0kW outdoor unit, supply and final install$4,139
TotalFully completed 49m² extension$240,079

That total leaves out the deck and the retaining wall. The client added both partway through the build, so they aren't extension costs.

Scroll the table sideways →

Not in the total · incl GST
ItemDescriptionCost
Deck and retaining wallLabour and materials for both, added partway through the build$42,852

One thing kept the groundwork cheaper here than on most jobs. Seventeen piles drilled to 1800mm bring up a lot of dirt, and usually all of it has to go: a Posi-Track to cart it out to a truck, then the truck to take it away and dump it. We didn't need any of that. The section sloped, so we moved the spoil outside the building line and used it to build the land up and help flatten the slope. On most jobs you'd need to allow for taking it away, on top of the drainage and foundation line above.

The back yard from above, with rows of drilled pile holes, a small digger and a builder clearing a hole with a shovel
The 17 pile holes being drilled, each to 1800mm to reach solid clay.

What's in a 49m² extension?

Here is what that money built:

  • Master bedroom with walk-in robe sized for wheelchair access
  • Fully accessible ensuite with curbless level-entry shower, accessible WC, and wall-hung vanity
  • Open-plan living area with stacker slider out to the deck and Velux skylights overhead
  • Timber overlay flooring through the bedroom and living area
  • Pile foundation: 17 piles designed to NZS 3604, drilled to 1800mm to reach 600mm of embedment in competent clay
  • Mono-pitched roof at 8 degrees in long-run colour steel
  • Mixed cladding: rusticated weatherboards on visible elevations, corrugated steel on one rear elevation
  • R2.8 wall insulation, R6.0 skillion roof insulation, R1.4 underfloor
  • Thermally broken Low-E double glazing throughout
The timber wall and roof framing of the extension standing on its piles, with a builder at a drop saw inside
The extension at framing stage, before the deck was built.
The finished extension seen from the deck: white weatherboards, a glass sliding door on the left and open folding doors into the living area on the right
The same side finished, seen from the deck. The bedroom is on the left and the living area is on the right.

Which decisions saved money?

Three decisions saved the most money on this job. All three were made before the build started.

Why is 49m² better than 50m²?

This site is in Auckland's stormwater flow overlay. Council's planner told our draftsman that if the addition went over 50m², it would need an engineered stormwater tank and resource consent on top of building consent.

We worked with the designer to keep the extension at 49.16m². The client got the same rooms, with no detention tank and no resource consent. For comparison, our draftsman's last similar job, in Beachlands, needed an engineer, a geotech report and a survey, and came to about $17,000 in design and consent fees. Here the design and consent fees came to $12,854.

Why a mono-pitched roof with parapets?

The parapets on three sides aren't just there for the look, they saved the cost of forming a soffit on those sides. The roof is one simple slope at 8 degrees, so the rafters are plain lengths of timber. You can pick those up off the shelf at your local Bunnings or PlaceMakers. Trusses have to be designed and made to order, and that takes time. Here there was no truss design fee and no wait.

Builders at work inside the extension's timber wall framing, with the roof rafters running across overhead
The rafters going on. Plain timber lengths, no trusses.
The extension's grey corrugated steel roof from above, with two skylights, flashings and a raised parapet edge, and scaffolding around it
The finished roof, with all the flashings completed.

Do you need an architect for an extension?

Not for a straightforward one. If the structure is conventional, a draftsman who is a licensed building practitioner can draw it for a lot less. The full set of plans here, ready for building consent, came to $6,021.

It also helped that the build sat within NZS 3604, the standard for timber-framed buildings. Inside that standard, a builder can frame a conventional house without a structural engineer's design. That meant no engineer's fee, no PS1 and no engineer reviewing changes made on site. It also makes getting the code compliance certificate (CCC) easier at the end.

How did we build it for a wheelchair?

These are the details we built in, and why.

How do you get rid of the lip at the bathroom door?

Normally the tiles and what's under them finish about 20mm higher than the floor around them, which leaves a small lip at the doorway. In a wheelchair that lip is a hazard, and it's a nuisance every single day.

At framing stage we checked the tops of the bathroom floor joists down by 20mm, which means cutting 20mm off the top of each one. Once the underlay and tiles went on, the bathroom floor finished at exactly the same height as the timber floor in the bedroom next door. There's no lip and no threshold strip to catch on. Checking a joist makes it shallower, so we added extra bearers underneath to make up for it.

The extension's timber floor joists with plywood flooring part laid and a builder marking a sheet; at the bottom right a lower grid of joists and nogs where the bathroom will be
The floor going down. Bottom right is the bathroom, where the joists are checked down 20mm and the nogs sit at 400mm centres.

How did we make the shower and the decks step-free?

The shower has no kerb. The floor falls gently to a drain, with nothing between the wet area and the rest of the room. With the joists checked down as well, the client can get from bed to ensuite to shower without crossing a single step.

The ensuite walls and floor coated in blue waterproofing membrane
BeforeThe ensuite waterproofed, before tiling.
The finished ensuite: grey tiled walls and floor, a toilet, a shower with no kerb, grab rails and a shower bench
AfterThe finished ensuite. The floor runs level from the door to the shower.

Running a laser level through the existing house turned up something nobody had noticed in years of living there: the kitchen and lounge floors sat at slightly different heights. That left the existing deck off the lounge a little higher than the new one. Where the two decks meet, we built a long, gentle ramp. You barely feel it underfoot and you can't see it from any normal angle. The whole ground floor and both decks are now one continuous accessible space.

Read the full detail on the accessible bathroom, with its own cost breakdown

What changed partway through the build?

We lodged two minor variations with the council during the build. That's normal on an extension. As the designer wrote on the consent cover sheet, all additions have a surprise element once walls are opened up.

Why did the roof framing change at the fireplace?

At roof framing stage, the rafters as drawn didn't work around the existing brick fireplace. We worked it out on site, framed it the way that worked structurally, then had the designer redraw the detail to match what we'd built. An extra skylight went into the same variation.

That comes from more than 30 years on the tools. When a detail on the plans doesn't work on site, we know what will work, and we know what the council needs to see. So we don't stop the job and wait weeks for new drawings. We build it right, tell the draftsman what to draw, and lodge the change. The roof still does the same job structurally, and the build never stopped.

Why did the cladding change on the back wall?

The consent specified rusticated weatherboards all round. Partway through, the back wall changed to corrugated colour steel to match the roof. Cladding is part of the consent, so the change needed a variation.

A wall clad in dark vertical corrugated steel, seen along a scaffold walkway
The back wall in corrugated colour steel, to match the roof.

Want a number for your own job?

Or call 0800 BUILTWELL · 0800 284 589

We reply within one working day. No sales pitch. We only use your details to get back to you.