Case study · East Auckland
A 49m² Auckland extension, costed honestly
$240,079Total incl GST. $4,900 per m², completed 2026
See the cost breakdownEvery figure on this page comes from the invoices and timesheets on this build. Homeowners often ask us what an extension actually costs in Auckland, so here is one of ours, line by line.
By Karl Updated November 2026

How this job compares: our Auckland extension cost guide puts it side by side with our other jobs.
What did we build in Mellons Bay?
A 49m² single-storey extension on the back of a two-storey house in Mellons Bay. It added a master bedroom with a walk-in robe, an ensuite and an open-plan living area that opens onto a deck. The client lives with mobility needs, so it had to give real wheelchair access, not just the code minimum.


It is 49m² on purpose. Past 50m² the job would have needed a stormwater detention tank and resource consent. There's more on that further down.

What did it cost, line by line?
$240,079 including GST for the finished extension, or $4,900 per m². Nothing below is rounded, and nothing is averaged against other jobs. These are from 2026.
Scroll the table sideways →
| Item | Description | Cost |
|---|---|---|
| Construction labour | Skilled trade labour at commercial rates | $77,447 |
| Construction materials | Timber, fixings, GIB, Pink Batts, Ecoply, hardware | $49,404 |
| Aluminium joinery | Stacker slider, bifold, awning, hinged door, thermally broken Low-E | $19,600 |
| Flooring | Timber overlay plus underlay and prep | $19,186 |
| Electrical | Rough-in, heat pump pre-pipe, fit-out, switchboard upgrade | $11,776 |
| Drainage | Drainage, stormwater connections, pile drilling, foundation work | $10,820 |
| Council consent fees | Processing, inspections and levies, passed through at cost | $6,833 |
| Tiling | Porcelain tile, tiling labour, waterproofing, adhesive | $7,595 |
| Wall cladding | Rusticated weatherboards plus corrugated steel to one rear wall | $7,247 |
| Plumbing | Bathroom rough-in, hot water cylinder, accessible fittings | $6,782 |
| Roof cladding | Long-run colour steel skillion roof at 8 degrees | $6,996 |
| Bathroom fittings | Vanity basin, accessible WC, level-entry shower drain, mixers | $6,233 |
| Design and drafting | Full BC-ready plan set by an LBP-registered draftsman | $6,021 |
| Heat pump | Daikin 5.0kW outdoor unit, supply and final install | $4,139 |
| Total | Fully completed 49m² extension | $240,079 |
That total leaves out the deck and the retaining wall. The client added both partway through the build, so they aren't extension costs.
Scroll the table sideways →
| Item | Description | Cost |
|---|---|---|
| Deck and retaining wall | Labour and materials for both, added partway through the build | $42,852 |
One thing kept the groundwork cheaper here than on most jobs. Seventeen piles drilled to 1800mm bring up a lot of dirt, and usually all of it has to go: a Posi-Track to cart it out to a truck, then the truck to take it away and dump it. We didn't need any of that. The section sloped, so we moved the spoil outside the building line and used it to build the land up and help flatten the slope. On most jobs you'd need to allow for taking it away, on top of the drainage and foundation line above.

What's in a 49m² extension?
Here is what that money built:
- Master bedroom with walk-in robe sized for wheelchair access
- Fully accessible ensuite with curbless level-entry shower, accessible WC, and wall-hung vanity
- Open-plan living area with stacker slider out to the deck and Velux skylights overhead
- Timber overlay flooring through the bedroom and living area
- Pile foundation: 17 piles designed to NZS 3604, drilled to 1800mm to reach 600mm of embedment in competent clay
- Mono-pitched roof at 8 degrees in long-run colour steel
- Mixed cladding: rusticated weatherboards on visible elevations, corrugated steel on one rear elevation
- R2.8 wall insulation, R6.0 skillion roof insulation, R1.4 underfloor
- Thermally broken Low-E double glazing throughout


Which decisions saved money?
Three decisions saved the most money on this job. All three were made before the build started.
Why is 49m² better than 50m²?
This site is in Auckland's stormwater flow overlay. Council's planner told our draftsman that if the addition went over 50m², it would need an engineered stormwater tank and resource consent on top of building consent.
We worked with the designer to keep the extension at 49.16m². The client got the same rooms, with no detention tank and no resource consent. For comparison, our draftsman's last similar job, in Beachlands, needed an engineer, a geotech report and a survey, and came to about $17,000 in design and consent fees. Here the design and consent fees came to $12,854.
Why a mono-pitched roof with parapets?
The parapets on three sides aren't just there for the look, they saved the cost of forming a soffit on those sides. The roof is one simple slope at 8 degrees, so the rafters are plain lengths of timber. You can pick those up off the shelf at your local Bunnings or PlaceMakers. Trusses have to be designed and made to order, and that takes time. Here there was no truss design fee and no wait.


Do you need an architect for an extension?
Not for a straightforward one. If the structure is conventional, a draftsman who is a licensed building practitioner can draw it for a lot less. The full set of plans here, ready for building consent, came to $6,021.
It also helped that the build sat within NZS 3604, the standard for timber-framed buildings. Inside that standard, a builder can frame a conventional house without a structural engineer's design. That meant no engineer's fee, no PS1 and no engineer reviewing changes made on site. It also makes getting the code compliance certificate (CCC) easier at the end.
How did we build it for a wheelchair?
These are the details we built in, and why.
How do you get rid of the lip at the bathroom door?
Normally the tiles and what's under them finish about 20mm higher than the floor around them, which leaves a small lip at the doorway. In a wheelchair that lip is a hazard, and it's a nuisance every single day.
At framing stage we checked the tops of the bathroom floor joists down by 20mm, which means cutting 20mm off the top of each one. Once the underlay and tiles went on, the bathroom floor finished at exactly the same height as the timber floor in the bedroom next door. There's no lip and no threshold strip to catch on. Checking a joist makes it shallower, so we added extra bearers underneath to make up for it.

How did we make the shower and the decks step-free?
The shower has no kerb. The floor falls gently to a drain, with nothing between the wet area and the rest of the room. With the joists checked down as well, the client can get from bed to ensuite to shower without crossing a single step.


Running a laser level through the existing house turned up something nobody had noticed in years of living there: the kitchen and lounge floors sat at slightly different heights. That left the existing deck off the lounge a little higher than the new one. Where the two decks meet, we built a long, gentle ramp. You barely feel it underfoot and you can't see it from any normal angle. The whole ground floor and both decks are now one continuous accessible space.
Read the full detail on the accessible bathroom, with its own cost breakdown
What changed partway through the build?
We lodged two minor variations with the council during the build. That's normal on an extension. As the designer wrote on the consent cover sheet, all additions have a surprise element once walls are opened up.
Why did the roof framing change at the fireplace?
At roof framing stage, the rafters as drawn didn't work around the existing brick fireplace. We worked it out on site, framed it the way that worked structurally, then had the designer redraw the detail to match what we'd built. An extra skylight went into the same variation.
That comes from more than 30 years on the tools. When a detail on the plans doesn't work on site, we know what will work, and we know what the council needs to see. So we don't stop the job and wait weeks for new drawings. We build it right, tell the draftsman what to draw, and lodge the change. The roof still does the same job structurally, and the build never stopped.
Why did the cladding change on the back wall?
The consent specified rusticated weatherboards all round. Partway through, the back wall changed to corrugated colour steel to match the roof. Cladding is part of the consent, so the change needed a variation.