Extension cost guide · Auckland

What an extension costs in Auckland

$4,900

Per m², incl GST. A 49m² single-storey extension, Mellons Bay, 2026.

Our 49m² single-storey extension in Mellons Bay cost $4,900 per m² including GST, or $240,079 all up. A Howick house we took from 170m² to 300m² cost $4,271 per m², and a 162m² house on Waiheke cost $7,589. Every figure on this page comes from our own jobs.

The timber frame of the Mellons Bay extension on its piles beside the existing house, with a builder at a drop saw inside

$4,900

Per m² incl GST. Mellons Bay, a 49m² extension

$4,271

Per m² incl GST. Howick, a 170m² house taken to 300m²

$7,589

Per m² incl GST. Waiheke, a 162m² house

49m²

On some sites, staying under 50m² skips a stormwater tank and resource consent

What does an extension cost in Auckland?

It depends on the size, the ground and the finish, so here are three of ours with the real numbers. All of them include GST, and each one links to the full itemised breakdown.

Three Builtwell extensions, incl GST
JobWhat we builtTotalPer m²On site
Mellons Bay49m² single-storey rear extension with an accessible ensuite, 2026$240,079$4,90014 weeks
Howick1960s block house renovated and extended from 170m² to 300m², with 114m² of decks, retaining and earthworks$1,281,230$4,27133 weeks
Waiheke IslandOld house renovated and extended to 162.2m². The total includes the driveway, wastewater and island travel; per m² is the house alone ($1,231,015)$1,734,976$7,589About 50 weeks

Scroll the table sideways →

Bigger jobs often work out cheaper per m², because the expensive parts are spread over more floor. Howick is the cheapest per m² of the three because it's 300m². Waiheke is the dearest: an old house with problems under every floor.

Building in Howick? See what a Howick extension costs. Need a bathroom for a wheelchair user in the extension? Here's what an accessible wet room costs.

What makes one cost more than another?

What moves the price
ItemWhat to know
FoundationsPiles cost less than a slab. Soft ground costs more, whatever you choose: at Mellons Bay we drilled to 1800mm before we hit solid clay.
CladdingSome claddings cost more than others. Cedar costs more than pine weatherboard, but pine weatherboard lasts longer.
JoineryThe Building Code's energy rules make plain aluminium windows hard to get through consent in Auckland. Thermally broken frames with Low-E double glazing usually get there.
Kitchen and bathroom finishesThe tapware, vanity, toilet and tiles you choose can change the price of a bathroom a lot.
What's behind the wallsRotten framing, asbestos, undersized lintels. You find out when the walls come open, so keep some money aside.

How does getting onto your site change the price?

Access adds up. It comes down to:

  • How far we have to park, because we're back and forth to the van for tools all day.
  • Whether we can unload materials close to the work.
  • Whether there's somewhere to store materials out of the way.
  • Whether a rubbish bin fits close by without being in the way.
  • Whether there's a toilet we can use, or a portaloo has to go in.

In the central suburbs, parking alone costs money, because Auckland Transport is quick with a ticket.

What kinds of extension are there?

An extension is any new floor area added to a house. It usually takes one of four shapes.

  • Single-storey, at the back or side. The most common.
  • A second storey. More structural work, because the house underneath has to carry it.
  • An attic conversion or dormer. Turning roof space into rooms. Stairs, dormer windows and strengthening come into it.
  • A sleepout or granny flat. A separate building on the same section. Since January 2026, a new single-storey granny flat up to 70m² doesn't need building consent, and usually not resource consent either. It has to sit at least 2m from the house and the boundaries, be drawn by a licensed designer and built by licensed trades, and you need a PIM from council before you start. Ask us whether yours qualifies.

For an extension, yes, almost always. For a granny flat up to 70m², often not. There are two kinds of consent, and people mix them up.

Building consent checks the build against the Building Code: foundations, structure, weathertightness, insulation, plumbing and electrical. An extension needs one. Auckland Council issues it.

Resource consent checks the plans against the Auckland Unitary Plan: how close you build to the boundary, how high, and how much of the section ends up covered. You don't always need it.

The height to boundary rule protects the neighbours' sun. In most Auckland residential zones, the building has to stay under a line that starts 2.5m up at the side and back boundaries and slopes in at 45°.

Why 49m² beats 50m²

On sites in Auckland's stormwater flow overlay, adding more than 50m² of roof or hard surface brings in resource consent and an engineered stormwater tank. The Mellons Bay site is in that overlay. Council's planner told our draftsman that if the addition went over 50m², it would need a tank and resource consent. So we kept the extension to 49.16m². The client got the same rooms, with no tank and no resource consent.

Do you need an architect or an engineer?

Usually not. For a design-led or unusual house, an architect earns their fee. For a plain extension with normal framing, a licensed draftsman can draw it, for a lot less. The full consent-ready plans for Mellons Bay came to $6,021 including GST. Our draftsman also kept that job clear of an engineer, a surveyor and a geotech report, which saved the client about $5,000.

We work closely with the draftsmen and engineers we trust, so you're not finding and managing them yourself, and the plans are drawn the way we build. If you've already got your own designer or engineer, we'll work with them, and if you've got plans drawn, we'll price them.

The same goes for an engineer. Most house extensions can be designed to NZS 3604, the standard for timber-framed buildings. The draftsman uses its span tables and bracing rules, so there's no engineer's fee and no PS1. Very high wind zones, soft ground, odd shapes or long spans take you outside NZS 3604, and then you do need one. We'll tell you if that's you.

How long does an extension take?

Here's how long each stage took on our 49m² Mellons Bay extension.

The three stages at Mellons Bay
StageWhat happensHow long
PlansOur draftsman sent the first sketch in early June 2025. The full plans were lodged for consent three weeks later.3 weeks
ConsentLodged on 25 June, approved on 5 August. Council asked for a geotech report partway through. Our draftsman showed them the site didn't need one, which saved the client the cost of it.6 weeks
BuildOur 49m² Mellons Bay extension took 14 weeks. The Howick job, which took a house to 300m², took 33. Waiheke took about 50 weeks on site, over 14 months. Second storeys take longer. Everything is done off scaffolding, so we're up and down it all day, and every material has to be lifted up to where we're working.14 weeks

Scroll the table sideways →

How we work

How we price variations

A variation is work that wasn't in the original price. Most of them come from fixing a problem nobody could see until the walls or floor came open, or from a change in the design from the client, so they're hard to price before we start. Where we can, we give you a fixed price first. Where we can't, we give you an indication, then charge for the time and materials the work actually takes.

Going over 50m² without noticing

On a site in the stormwater flow overlay, a 55m² extension can cost a lot more than a 49m² one, and the extra 6m² isn't why. It's the consent and stormwater work that come with it.

A step into the bathroom

Where we can, we drop the bathroom floor so the tiles finish flush with the rooms around it. No lip at the door, whether or not anyone uses a wheelchair. It depends on what's underneath. We can't do it over a room below, and on a concrete slab it has to be planned at the foundation stage. If you need a bathroom for a wheelchair user, the accessible bathroom page has the price of one, line by line.

Who are we?

Builtwell is a licensed building company based in Howick. Karl has been on the tools for 31 years. We work across central and East Auckland, from Howick, Mellons Bay, Bucklands Beach, Half Moon Bay, Botany and Pakuranga through to Remuera, St Heliers, Mt Eden and Pt Chev. We take on Waiheke jobs when they suit, like this Onetangi renovation.

We put our real costs on this site so you know what you're looking at before you call. We'd rather sort out the 50m² line, the draftsman and the framing details before the build than fix them during it. And we build accessible homes properly.

If you're planning an extension, tell us about it. We'll tell you straight whether it makes sense, roughly what it'll cost and how long it'll take. If we're not the right builder for it, we'll say so.

Costs are from real Builtwell jobs, GST included. Every trade is licensed where the law requires it.