Case study · Ponsonby

A Ponsonby villa renovation: what it cost

$470,533

Total incl GST, completed 2025

See the cost breakdown

A villa renovation in Ponsonby: two new bathrooms, a rewire, kitchen and bedroom changes, then off-street parking, new fences and gates out the front. Here's what it all cost, trade by trade.

The new main bathroom in the Ponsonby villa: a wall-hung vanity with a lit oval mirror, a walk-in shower, and a freestanding bath under the window

How this job compares: our Auckland renovation cost guide puts it side by side with our other jobs.

What did we do to this villa?

The house started out as a villa, and someone before us added a big, very modern extension to it.

Most of the work was inside. Then we finished out the front, with off-street parking, fences and gates.

Inside:

  • Rebuilt the main bathroom, with a freestanding bath, a walk-in shower and underfloor heating
  • Rebuilt the master ensuite, with the floor framing strengthened for the new shower, and underfloor heating
  • Moved the master bedroom door and took the wardrobe wall up to the ceiling
  • New painted kitchen panels and island, a wall cabinet, and the pantry reworked and tiled
  • Sanded and clear-coated the plywood kitchen ceiling
  • Straightened the living room ceiling, and redid the old, badly done patches where fireplaces and walls had been taken out
  • Took out a window and closed in the wall
  • Rewired lights and power to new positions, with a new switchboard, an intercom and an alarm
  • Two new heat pumps
  • Plastered, stopped and painted inside

Outside:

  • Painted one side of the house and the roof
  • A new timber side fence, and an aluminium fence along the front wall
  • A sliding car gate with automation, and a pedestrian gate
  • Footings, a block wall and new paving to make off-street parking
  • Outside lights and a security sensor
The old main bathroom, with white floor tiles, a blue border and a pedestal basin
BeforeThe main bathroom before.
The finished main bathroom: a long room with a wall-hung vanity and lit oval mirror, a walk-in shower, and a freestanding bath under the window
AfterThe main bathroom after.
The old ensuite, with green mosaic tiles and a timber vanity
BeforeThe ensuite before.
The new ensuite, with green tiles, a glass shower, a timber vanity and a round mirror
AfterThe ensuite after.
The main bathroom floor stripped back to the joists, with new framing nogged in between
The main bathroom floor, reframed before the new floor and tiles went down.
The new main bathroom, with marble-look tiles, a lit shower niche and a freestanding bath
The same bathroom, finished.
The living room, with a straight white board-and-batten ceiling, track lights and two red pendant lights
The living room, with the ceiling straightened and the old patches gone.

What did it cost?

The whole job: $470,533 including GST.

Scroll the table sideways →

Ponsonby villa renovation, all figures incl GST.
ItemDescriptionCost
Builtwell labour1,763 hours$123,102
ElectricalRewire, switchboard, lights, heat pumps, intercom and alarm$77,771
Plastering, stopping and paintingInside, one side of the house, the roof and the fences$68,327
Building materialsTimber, ply, gib, fixings and trims$47,508
Project management and site costsBins, scaffold, hire and deliveries$31,829
Kitchen and wardrobesPainted kitchen panels and island, wardrobe fit-out$31,125
Fences and gatesSide and front fences, sliding gate with automation, pedestrian gate$29,416
Off-street parkingFootings, a block wall and paving$22,959
Tiling and waterproofingMain bathroom, ensuite and pantry$21,770
Plumbing and drainageBoth bathrooms, the kitchen and a drain camera check$16,726
TotalThe whole job$470,533

How long did it take?

We started at the end of May 2024 and were on site most weeks until late November. Our crew put in 1,763 hours. The plumber, electrician, tiler, plasterer, painter, block layer and the kitchen makers worked around us, and we ran all of them. We came back for some finishing in February 2025.

What was the hardest part?

Getting the fall into the two new showers. A tiled shower floor has to slope to the drain, and that slope comes out of the floor framing. Here the joists were only 90x45, what we call 4x2, so there was very little depth to work with. We doubled the joists up and put support in underneath to carry the new showers. The ensuite shower has a channel drain along the wall, so we also had to make a rebate in the floor for it to sit in. And there were pipes running everywhere under there to work around.

Looking down through the opened-up ensuite floor: shallow 4x2 joists, new framing, and waste pipes running between them
Under the ensuite floor: 4x2 joists and pipes everywhere.
The finished ensuite: green tiles, a glass shower with a black rain shower, a round lit mirror and a curved timber vanity
The same ensuite, finished.

What else did we do here?

The block wall, the paving and the sliding gate were there to create off-street parking, which is close to impossible to find in Ponsonby. They were part of the plan from the start, along with the fences. We did them towards the end of the job: the footings were dug in September, the block wall went up in October and the fences in November.

The side of the villa before: outside stairs beside an old corrugated fence, overgrown with bamboo
BeforeThe side fence before: old corrugated iron and bamboo.
A new timber paling fence running beside the outside stairs
AfterThe new side fence.
A new block wall and paving for off-street parking, with temporary site fencing still up
The block wall and paving for the new off-street parking, just finished.