Case study · Waiheke Island
Waiheke renovation: renovate or rebuild?
$1,734,976Total incl GST, completed 2024
See the cost breakdownThis Waiheke Island renovation was meant to open an old Onetangi house up to the sea. A couple of weeks in, the client told us they should have knocked it down and built new. They were right.
By Karl Updated November 2026
Project specs
- Location
- Onetangi, Waiheke Island
- Type
- Renovation and extension
- Floor area
- 162.2m² (the under-house storage isn't included)
- Total cost
- $1,734,976 incl GST
- The house
- $1,231,015 incl GST
- Per m²
- $7,589 incl GST
- Variations
- $190,189 incl GST
- Deck
- About 75m²
- On site
- About 50 weeks, over 14 months
- Completed
- 2024


How this job compares: our Auckland extension cost guide puts it side by side with our other jobs.
Should they have knocked it down?
Once we started the demolition, the true condition of the house started to show. The bearers weren't what the plans said. A few of the piles were on quite a lean. Under the cladding, there was rot in the structure.
We instructed the architect to add a new row of piles, because the excavation for the garage would have undermined the existing ones. We also asked for an engineer. The client agreed the next morning. Their view: there was no point spending all that money and having the house slide off its piles down the hill.
Not long after, with more turning up, they said it straight: they should have knocked it down and built new. We agree. A new build would have given them a house designed around them, instead of one squeezed into the tight shape of the old one. The extension on its own would have been a straightforward build.

The decision to renovate was made before we were involved. If we'd been at those early meetings and inspected the house first, we'd have recommended against it.



What did we find under the floors?
Once the walls came out, the floor turned out to be at four noticeably different heights. The living room was 50mm out from one side to the other. The laundry sat 20mm above the kitchen.


The old tongue and groove flooring came up. Underneath, some joists had to be fixed or replaced. In places the bearers had rotted through, so new piles and bearers went in. One boundary joist was rotten and came out. Then a new floor went down over the lot.

Some of the walls we kept were sitting on the old floor. To get the new floor under them, we propped each wall, cut out its bottom plate, ran the flooring through and rebuilt the wall on top.
Getting the floors level and the walls straight took 461.5 hours of labour. Our price had no line for re-levelling the floors, because nobody knew they needed it.



Why were the walls so much work?
A lot of the old walls weren't straight at all. The kitchen and laundry walls were 80mm out of square, so we pushed the outside laundry wall out to bring them back square. One load-bearing wall had been built from 70mm timber. We rebuilt it plumb in 90mm. The studs were at spacings that didn't suit a standard 1200mm sheet, some were over height, and some timber was rotten or black with mould.
One wall had to be reframed altogether to take a new window.
The roof was short of rafters in the living area, and its fixings weren't up to code. We added rafters, redid the eaves and brought the fixings up to standard.
What was under the house?
Someone had poured a concrete floor under there at some point, probably in a few goes, and not well. It sat on a big slope. The half-height concrete walls around it were in bad shape. One of them was load-bearing and had no footing under it. There were old nails everywhere. It had probably been where the lawnmower lived.
So we propped the house up, dug out underneath the existing concrete walls and built a footing under them. Builders call that underpinning.
Then we dug the room out, built steps down, put a door on, poured a new slab, extended the concrete walls up and clad it from the outside. Inside, we strapped the walls, put in insulation and lined them with Gib.
All of this was a variation, meaning work that wasn't in the original price. It's the under-house storage line in the variations table below: $20,817 including GST. The cost is in the work: breaking up and removing the old concrete, then supporting the house while we dug under the existing walls by hand.
The client now has a dry, usable storage room, 3 or 4m², where there used to be a rough space under the house. It isn't counted in the floor area below.


How did the client keep track?
Every week, we sent the client a detailed report. Each one had photos from that week, marked up with notes, so they could see what we'd found and what we'd done about it. We do this on every job, all the way through the build.

What does building on Waiheke add?
We tried to use island trades first. At the start of the job we asked Waiheke subtrades to quote, and not one got back to us, even after we chased them. On an island, a trade who doesn't turn up when they said they would can hold a job up for days, and that costs real money. So we brought our own Auckland subbies, the same ones we use on every job. The crew came over on the ferry and stayed on the island, and we bought materials from the local PlaceMakers. Ferry and barge fares and accommodation came to $85,653 including GST. We think it was worth it.
We had skip bins at first, but the truck couldn't get up the hill, so most of the rubbish went to the tip on our own trailer. Big deliveries came up by HIAB.
The section needed work as well. The concrete driveway is about 80 metres long, up from the road, with a parking area at the top: about 280m² of concrete in all. There's also a new wastewater treatment system and drainage.
Outside, the deck is about 75m². The outdoor fireplace was a late addition: the client decided in April 2024 that it was spendy but they wanted it. The supplier wouldn't deliver to Waiheke, so it came over on the barge, and even the smallest truck couldn't get up the back of the site. We found another way in.




What did it cost?
$1,734,976 including GST, for the whole job: the house, the variations, the driveway, the wastewater system and the travel. A variation is work that wasn't in the original price. The outdoor fireplace isn't in the total. The client bought that direct from the supplier.
Scroll the table sideways →
| Item | Description | Cost |
|---|---|---|
| The house (162.2m²) | Including the deck (about 75m²). The per m² rate comes from this line | $1,231,015 |
| Extras and variations (below) | Each priced on its own, in the next table | $190,189 |
| Driveway | About 80 metres long, with a parking area at the top. About 280m² of concrete | $157,722 |
| Ferry, barge and accommodation | Fares for crew and materials, and somewhere to stay on the island | $85,653 |
| Wastewater system and drainage | New treatment system, old tank out | $62,407 |
| Topsoil and levelling the lawn | $7,990 | |
| Total | The whole job | $1,734,976 |
The house works out at $7,589 per m² including GST. That includes the deck, but not the variations, the driveway, the wastewater system or the travel, so it's the price of the house itself.
The variations are priced on their own, so you can see what each one cost:
Scroll the table sideways →
| Item | Description | Cost |
|---|---|---|
| Floors and walls | Re-levelled, new piles and bearers, reframed and straightened | $63,205 |
| New flooring laid over the levelled floor | $33,208 | |
| Under-house storage | Dug out, footings, slab, walls, cladding and waterproofing | $20,817 |
| Soffits | Hardiegroove and battens outside, and under the deck | $17,004 |
| Grooved linings and villa board inside | $16,676 | |
| Plumbing, electrical and tiling extras | Bathroom changes, meter move, range hood | $15,146 |
| Roof | Missing rafters, eaves, fixings brought to code | $11,443 |
| Back door landing and steps, and skirtings after the new floor | $10,503 | |
| Rubbish runs, with no truck access | $2,187 | |
| Total | All the variations | $190,189 |
Our price had a contingency of 200 hours in it, for things nobody could see. If we don't use it all, the client isn't charged for the hours left over. Unfortunately, this house had one hidden problem after another. The floors, walls, roof, soffits and storage alone took more than 880 hours.
How long did it take?
We started in September 2023 and aimed to finish by the end of May 2024. The council's final inspection passed on 21 October 2024, about five months late. New piles and the storage room both needed design changes and council sign-off, concrete was hard to get on the island, and every surprise in the old house added time. The longest stop was about six weeks in March and April 2024, waiting on new drawings for the storage room. Across the 14 months, we were on site for about 50 weeks. The code compliance certificate came through in March 2025.
The client had their housewarming on the deck. They both work long hours. One summer evening, they sent us a photo of the family sitting around the outdoor fireplace, just relaxing. After all the work and money that went into the place, that was the pay-off.
A year after the housewarming, someone walked up the drive and offered to buy the house. They said no.


Renovate or rebuild: what we'd tell you now
We'd want to inspect a house like this before the design is settled. That's when we can tell you what's hiding in it.
If the plan is to move most of the walls in an old house, we'll give you a straight answer first: would we renovate it, or knock it down and build new?
We can't see everything before the walls come out, but we can see a lot. We run a level across the floors room to room, get under the house, and take a few linings off where it looks tired.
Building on the island is very doable. Just budget for getting there: here it was about one dollar in every twenty.