Case study · Westmere

A full renovation of a 1940s Westmere house: what it cost

$554,782

Total incl GST

See the cost breakdown

We gutted and rebuilt the inside of a 1940s weatherboard and brick house in Westmere, and did up the sleepout. Here's what the whole job would cost today.

The open-plan kitchen and dining room under the open cathedral ceiling, with wrapped timber beams and skylights

How this job compares: our Auckland renovation cost guide puts it side by side with our other jobs.

What did we do?

Everything inside the house, and the sleepout. The garage was the only part we didn't touch.

In the house:

  • Stripped the inside back to the frame
  • New structural steel, so walls could come out for the open-plan living
  • Opened the kitchen, dining, lounge and study nook into one space, running through to a second living room
  • A gas fireplace between the two living rooms
  • Opened the ceilings up to the roof, cathedral style, with wrapped timber beams and skylights
  • New aluminium joinery, with bifolds out to the deck
  • Salvaged Matai floorboards, laid, sanded and finished
  • Installed the kitchen, a showroom floor kitchen the client bought
  • The main bathroom and the master ensuite, and underfloor heating
  • A timber batten balustrade on the stairs
  • New wiring and lighting, a heat pump, HRV and full insulation
  • New linings, stopped and painted throughout

The sleepout got a new roof on its extension, its own bathroom and hot water, plumbing and drainage, and a walk-in wardrobe.

Outside, we built the deck and patio, and did the drainage, the new power supply and the gas connection.

What changed in the floor plan?

Most of the walls in the middle of the house came out. The kitchen, dining and lounge became one long open space, running through to a second living room, with a gas fireplace between them. The old bathroom became an ensuite for the master bedroom, and a new main bathroom went in on the other side of the hall.

Floor plans before and after the renovation. Before: the walls that were taken out in grey. After: the new walls in yellow, with the rooms named.
Redrawn from the consent plans. The garage and the sleepout aren't shown.
The old kitchen before the renovation, with dark timber cupboards
BeforeThe old kitchen.
The new kitchen with a long island and timber floor
AfterThe new kitchen.
The old lounge before the renovation, carpeted with a low ceiling
BeforeThe old lounge.
The new lounge with the gas fireplace and Matai floor
AfterThe new lounge.
The house back to its frame, with the salvaged Matai floor going down
Back to the frame, with the salvaged Matai going down.
The old stairwell: carpeted stairs, a tiled ledge with pot plants, and a small chandelier
BeforeThe stairwell before.
The stair with its timber batten balustrade
AfterThe new timber batten balustrade on the stairs.

What did it cost?

Priced for today: $554,782 including GST.

Scroll the table sideways →

Westmere renovation, all figures incl GST, at today's prices.
ItemDescriptionCost
Builtwell labour2,337 hours$178,517
Building materialsTimber, gib, fixings and consumables$109,003
Plumbing and gasHouse and sleepout, gas fireplace and hot water$44,901
Matai flooringSalvaged boards, supplied and finished$33,366
Drainage and earthworksNew drainage, digging and cartage$27,166
ElectricalFull rewire, lighting, new power supply, underfloor heating$39,143
Painting, interiorThree coats through the house$24,421
Painting, exteriorFrom our price for it$23,436
Site costsBins, hire, concrete pump$21,530
TilingFloors and walls$20,034
Aluminium joineryWindows and doors$11,413
ScaffoldingHire$8,463
Structural steelBeams for the open-plan living$8,379
Glazing and shower glassGlass and shower screens$2,593
RoofingThe sleepout extension$2,417
TotalThe whole renovation$554,782

The kitchen units aren't in that total. The client bought a showroom floor kitchen, and we installed it.

How long did it take?

Our crew put in 2,337 hours over about 22 weeks, with the painter, plumber, electrician, tiler and the rest working around us. The painting and the gas fit-off finished about a month after our crew did.

What was the biggest change?

The ceilings. Partway through, the ceilings over the kitchen, dining and lounge were opened up, cathedral style, right up to the underside of the sloping rafters. That needed structural steel beams, which we packed out and wrapped in timber so they could be left on show. Each new beam puts its weight down at a point, so we had to carry those loads down through the floor to the storey below. It all went through council as a variation to the consent. It made the job cost more and take longer, but it's the first thing you notice when you walk in.

What changed along the way?

A lot. The job started from the architect's plans and grew as it went. The ceilings were one of 29 changes that went back through the council, the architect and the engineer as an amendment to the consent. The others included:

  • A floor-to-ceiling cavity slider in place of a standard-height one
  • The windows and doors in the master bedroom and living room moved
  • A new beam over the opening between bedroom 3 and the living room
  • A fixed skylight
  • A flue for the new gas fireplace

On top of those, the client added:

  • Timber wall panelling
  • The kitchen install
  • Painting inside and out
  • A new deck
  • New Matai flooring through the kitchen and lounge
  • Underfloor heating
  • Extra tiling
  • Upgraded plumbing
  • Extra earthworks
  • Landscaping
  • Work for a spa pool

Asbestos turned up at the start as well, and had to be cleared before the work could go ahead. Every one of these changes is in the price above.

The new main bathroom with white tiles and a timber vanity
The main bathroom.
The renovated sleepout from the garden
The sleepout.
The back of the house at dusk, opened up to the deck through the bifolds
The bifolds open the living rooms out to the deck.