Extension builder · Howick

Extension builder in Howick

$4,271

Per m², incl GST. What one of our Howick jobs cost.

Builtwell is an extension builder in Howick. One of our Howick jobs took a cold 1960s block house from 170m² to 300m². It cost $1,281,230 including GST, or $4,271 per m².

The Howick house from the back lawn after the extension, with the new deck

170 → 300m²

The house, before and after

33 weeks

On site

1800mm

Footings, drawn at 600mm

114m²

Of decks: an 80m² main deck and two smaller ones

What does an extension in Howick cost?

That job cost $1,281,230 including GST. It covers the extension, the renovation of the old house, an 80m² deck and two smaller ones, a retaining wall the length of the section and the earthworks. Over 300m², that's $4,271 per m².

Where the money went, Howick, all figures incl GST
ItemWhat it coversCost
Builtwell labourOur builders and apprentices$301,912
Building materialsTimber, cladding, decking, fixings and the rest of the PlaceMakers order$227,001
Earthworks and drainageClearing, cutting the section flat, cartage, hardfill, retaining, stormwater and sewer$177,372
Concrete and block foundationsFootings, slabs, block foundation walls and the concrete pours$95,804
Windows, doors and joineryDouble-glazed aluminium joinery, doors and garage doors$65,130
Design and consultantsDrawings, engineering and other consultants$61,821
Everything else13 more trades, from the kitchen to the council fees$352,190
TotalRenovation and extension, 170m² to 300m²$1,281,230

Scroll the table sideways →

All 19 lines are in the Howick case study, with the photos. To see how a Howick job compares with a small extension and an island one, the Auckland extension cost guide has them side by side.

What pushes the price up in Howick?

Usually the ground. The drawings had the footings going down about 600mm. We kept digging until we hit hard clay, at 1800mm. Every load of soft ground that comes out is a load of hardfill that comes in, compacted in layers with a geotechnical engineer checking it. About a fifth of what the job cost went into the ground before a wall went up.

Does your extension need a concrete slab?

Not always. The garage needed one. The living extension didn't, and we advised timber piles and a timber floor, which cost much less than a block foundation and a slab. The architect advised concrete so the floors would feel the same underfoot, and the client went with that. It cost significantly more. We've since built a job where the floor runs straight from concrete onto timber, and you can't tell.

Why use a Howick builder?

We're based in Howick and work across central and East Auckland, and we're licensed building practitioners. Karl has been on the tools for 31 years and was on site every day of the Howick job.

Every price on this site comes from our own jobs. If you're not sure what you want built yet, tell us about the house and the section. We'll come and look, and tell you straight what it's likely to cost.

All figures include GST. Every trade is licensed where the law requires it.

Planning an extension in Howick?

Or call 0800 BUILTWELL · 0800 284 589

We reply within one working day. No sales pitch. We only use your details to get back to you.